Safety Behaviour in the Construction Industry
|
|
|
Nick McDonald, Victor Hrymak
|
|
|
Background
There are a total of five construction inspectors in Northern Ireland
working with the Health and Safety Executive. The structure of this construction
group is comprised of four full-time inspectors reporting to one principal
construction inspector. All inspectors had an engineering background;
one electrical, two civil and one building management. The HSE recruits
employees from all sectors. The interviewees reported working as construction
inspectors over a period of five years to 5 months. The inspectors had
much experience working in the area, from 10-15 years in the field of
inspection. All inspectors were trained to a high degree.
Inspectors had successfully completed postgraduate diploma in safety management.
The HSE also offered regular training courses for inspectors including
legislation, COSSH, machinery guarding. New inspectors shadowed more experienced
inspectors for a short period of time, which allowed for on the job training.
There was a reported high level of cooperation amongst inspectors. On
occasion two inspectors conducted inspections together. Construction inspectors
have their own geographical area to cover.
Over one thousand inspections are conducted annually in Northern Ireland.
The principal inspector conducts approximately 100 per year.
Site Selection
The HSE inspectors had a structured systematic approach to selection of
sites for inspection. Inspectors reported that up to 80% of sites notified
the authority of works in progress or proposed works. The authority receives
approximately 500 notification per month. It was reported that two-thirds
of these would be inspected. A database of all notifications is maintained.
Notifications are classified into three categories:
- Large construction
works which require inspection,
- Construction
works which require communication with the architect,
- Smaller construction
works which will not be inspected e.g. small refurbishment's or roadworks
Complaints, accidents,
and fatalities take priority over scheduled inspection. All complaints
received by the authority area dealt with within ten days. Complaints
may be dealt with over the phone but may also require a site visit.
Inspectors emphasized the importance of being cost effective when planning
site inspections. Sites selected for inspection were done so according
to size, operation and degree of risk associated with the work. Based
on experience one inspector reported the bigger the site, the bigger the
risk. However other inspectors disagreed and reported that smaller sites
were more dangerous. All four inspectors agreed that the present method
for site selection was a fair system and could be improved upon with more
resources.
Site Inspection
Inspectors had a structured approach to site inspection. Inspectors reported
they commenced their inspection on approaching the site, taking heed of
any hazards visible from the road e.g. poor traffic management, poor housekeeping,
dirty roadways. All four inspectors requested to speak with a member of
the site management team on arrival, generally the contracts manager or
site foreman.
It was reported there were very few safety officers and safety representative
on site. Only one inspector reported a level of hostility on one previous
site inspected. Three of the four inspectors inspected safety documentation
prior to assessing site safety. One inspector stressed the importance
of speaking with the site operatives asking for their opinions on safety
matters relevant to the site. Inspectors always asked to be accompanied
on their site inspection, generally by the site foreman. This gave the
foreman an opportunity to make his/her own notes and verbally communicate
with the inspector.
Safety on sites
Inspectors rated safety as low to medium on construction sites in Northern
Ireland. Safety plans varied in both quality and quantity according the
inspectors. Larger sites tended to have comprehensive safety plans with
site-specific risk assessments. The inspectors attributed this to the
fact that the safety plan was devised internally with plenty of available
resources. Inspectors reported examination of subcontractors method statements,
which were considered very poor. One inspector felt very strongly about
the movement of subcontractors across the border where they have to comply
with Northern Ireland legislation. Subcontractors were unfamiliar with
the legislation requirements.
In general sites were not concerned with the method statements from subcontractors.
One inspector indicated that the presence of a safety plan on site was
a not a good indicator of safety performance. The inspector reported that
much of the safety documentation was there to "cover management" and meet
legislative requirements. Inspectors agreed involvement from subcontractors
had to be increased to improve site safety.
All inspectors believed that site safety was better with a full-time safety
officer on site. Main problems reported by inspectors on sites included
poor scaffolding, poor welfare facilities, falls from height, poor housekeeping,
lack of documentation, site security and machinery. One inspector reported
that 70% of the safety plans were generic, not site specific with the
use of water and electricity not addressed in the safety plan. The inspector
recommended that all safety plans should be 8/9 pages in length. Many
of the safety plans were not available on site as they were held in the
company's head office. Inspectors viewed this as an indicator of how active
the safety plan was on site.
All complaints were dealt with. Many of the complaints come from members
of the public, which may be anonymous. Complaints regarding access to
site by children, dirty roads and noise have been reported.
Following a site inspection, inspectors may issue prohibition notices
(PN) or improvement notices (IN) where necessary. These notices are followed
up with a letter of communication with accompanying relevant information.
The inspectors also reported conducting site re-inspection one week after
the PN had been served.
It was also reported that the level of management commitment to safety
varied across sites. Larger sites were generally more proactive regarding
safety management. All inspectors believed that management needed to take
responsibility for safety and involve operatives and subcontractors. Inspectors
reported that operatives believed "they had to get the job done quickly
without complaint", believing they had to work under dangerous conditions.
All inspectors stressed the importance of safety training for both management
and operative levels. Training on larger sites was reported better which
was attributed to access to resources e.g. mobile training unit. Some
smaller sites had no safety training. All inspectors welcomed the Registered
Skills Card scheme. To date up to 20% of operatives have been registered.
Inspectors attributed the main cause of site accidents to lack of resources
on site, stupidity, apathy, a lack of safety ownership and management
commitment to safety.
The Northern Ireland construction group has placed great emphasis on improving
site safety through conducting particular campaigns. These campaigns have
utilized local media to highlight the importance of secure and safe scaffolding.
Inspectors noted an improvement in site scaffolding since the introduction
of this campaign. Inspectors have recognized the importance of safety
at the planning and intend to involve planners and architects in preventing
safety problems at the early stages of design and construction.
Suggestions for improvement
- Increased resources
within HSE i.e. more inspectors
- Increase the
level and quality of training
- Health and
safety plan must be site specific
- Need for a
fundamental change in attitudes on construction sites
- Company and
site management need to take responsibility for safety
- Engage other
industries in safety campaigns
- More communication
and feedback to lower site level
Overall conclusions
Inspectors identified the areas for improvement and development in safety
management i.e. involvement of planners at early stages. They were very
positive regarding their future involvement in prevention of accidents
and fatalities. Inspectors felt very strongly about the importance of
safety training. There was a general consensus that larger sites were
better as they had access to resources, more ownership of safety plans
as they were developed internally.
Back to Contents
This paper appears in the eLCOSH website with the permission of the author
and/or copyright holder and may not be reproduced without their consent. eLCOSH is an
information clearinghouse. eLCOSH and its sponsors are not responsible for the accuracy of
information provided on this web site, nor for its use or misuse.
|
|