| Construction
Safety Council recommends filing out one of these before any project
begins- to help prevent electrocutions. |
Today's Date _____________
Job Number ____________
| Contractor
Name |
|
| Job
Address |
|
| Telephone
Number |
|
Fax
Number |
|
Before beginning
any project, you must first survey your work area to find power lines
at the job site. (See job site sketch on reverse side)
After finding all
of the power lines at your site, identify the activities you'll be doing
that may put you or your workers at risk. Mark one or more of the following:
Cranes (mobile or truck mounted) |
Aerial lifts |
Drilling rigs |
Dump trucks |
Backhoes/Excavators |
Ladders |
Long-handed tools |
Material Handling & Storage |
Other tools/high-reaching equipment |
Scaffolding |
Concrete pumper |
Other____________ |
After identifying
the power line and high-risk activities on our job site, we must determine
how to eliminate or control the risk of electrocution (a successful determination
is often reached only after consultation with the utility). Mark one or
more of the following:
Move the activity |
Use barrier protection (insulated sleeves) |
Change the activity |
Use an observer |
Have the utility de-energize the power line |
Use warning lines with flags |
Have the utility move the power line |
Use non-conductive tools |
| |
Use a protective technology |
| |
Insulated link
Boom cage guard
Proximity device
|
Always maintain your
minimum safe clearance distance from the power line, except when the utility
has de-energized and visibly grounded the power line.
|
Voltages
|
Distance
from Power Line
|
| Less than 50
kV |
10 feet |
| More than 50
kV |
10'+(0.4")(#
of kV over 50 kV) |
|
WARNING!
It is unlawful to operate any piece of equipment within 10' of energized
lines
|
Jobsite
sketch
(draw
in location of power lines and their proximity to construction site, include
such things as; proposed excavations, location of heavy equipment, scaffolding,
material storage areas, etc.)

Completed by_____________________
Date__________
Title_____________________
Approved by______________________
Date__________
Title_____________________
This paper appears in the eLCOSH website with the permission of the author
and/or copyright holder and may not be reproduced without their consent. eLCOSH is an
information clearinghouse. eLCOSH and its sponsors are not responsible for the accuracy of
information provided on this web site, nor for its use or misuse.
|