|
| These materials
were produced by the Division of Safety, Florida Department of Labor
and Employment Security, as part of a special OSHA program to reduce
work-related deaths in construction in California, Florida, and Texas.
Because Florida's funding for the program - CARE, or Construction
Accident Reduction Emphasis - ended in June 2000, the materials will
not be updated. The materials should be reviewed yearly for any needed
changes. |
Environmental Health and Safety Services (EHSS) developed this excavation
and trenching safety program to protect employees from safety hazards
that may be encountered during work in trenches and excavations. This
program is intended to assure that:
- Department that perform work in excavations are aware of their responsibilities
and have appointed one or more individuals within the department (the
Project Manager) to assure compliance with the requirements of this
program;
- The responsibilities of the departmental Project Manager and workers
are clearly detailed; and,
- All persons involved in excavation and trenching work have received
appropriate training in the safe work practices that must be followed
during this work.
This program includes provisions for employee training, hazard identification
and control, and work practices that must be followed while constructing
or working in or around an excavation or trench. The designated departmental
Project Manager is required to assure that:
- The procedures described in this program are followed;
- Employees entering excavations or trenches are properly trained and
equipped to perform their duties safely; and,
- All required inspections, tests, and recordkeeping functions have
been performed.
| SECTION |
PAGE TITLE |
| 1.0 |
INTRODUCTION |
| 1.1 |
Who Should Participate |
| 1.2 |
Safety Coordinator |
| |
|
| 2.0 |
DEFINITIONS |
| |
|
| 3.0 |
PROGRAM ELEMENTS |
| 3.1 |
Training and Duties of Program Participants |
| 3.2 |
Training and Duties of Workers |
| 3.3 |
Training and Duties of the Project Manager |
| 3.4 |
Contractor Awareness, Duties and Responsibilities |
| |
|
| 4.0 |
SPECIFIC EXCAVATION REQUIREMENTS |
| 4.1 |
Utilities and Pre-Work Site Inspection |
| 4.2 |
Protection of The Public |
| 4.3 |
Protection of Workers in Excavations |
| 4.4 |
Inspection by the Project Manager |
| |
|
| 5.0 |
REQUIREMENTS FOR PROTECTIVE SYSTEMS |
| 5.1 |
Protection of Employees in Excavations |
| 5.2 |
Design of Sloping and Benching Systems |
| 5.3 |
Design of Support Systems, Shield Systems,
and Other Protective |
| 5.4 |
Materials and Equipment |
| 5.5 |
Installation and Removal of Support |
| 5.6 |
Sloping and Benching Systems |
| 5.7 |
Shield Systems |
1.0
INTRODUCTION TO THE EXCAVATION AND TRENCHING SAFETY PROGRAM
The purpose of the
Excavation and Trenching Safety Program is to put in place work practices
and procedures that will protect employees from hazards that may be found
in or around excavations or trenches. This objective is met by:
Requiring each
department that performs work in excavations to name one or more persons
to serve as the departmental Project Manager.
- Training Project
Managers so they understand their duties and responsibilities.
- Requiring that
each Project Manager assure that all persons working in excavations
have been provided adequate training as required by this program.
- This program
has been designed to comply with Occupational Safety and Health Administration
(OSHA) standard 29 CFR 1926 Subpart P.
1.1
Who Should Participate
- All departments
that work in or around excavations must comply with the requirements
of this program.
- Other key participants
include:
- Workers who
work in or around excavations;
- Contractor’s
personnel, since the work that a Contractor performs can directly
affect the safety of persons working in or around excavations.
1.2
Safety Coordinator
- The Excavation
and Trenching Safety Program is administered by the Occupational Safety
Programs division of Environmental Health and Safety Services (EHSS).
EHSS will:
- Monitor
the overall effectiveness of the program;
- Assist
with atmospheric testing and equipment selection as needed;
- Provide
training for designated Project Managers;
- Assist
the departmental Project Manager with training of other departmental
employees;
- Provide
technical assistance to the departments as needed; and,
- Review
and update the program on an annual basis as necessary.
2.0
DEFINITIONS
Accepted engineering practices means the standards of practice required
by a registered professional engineer.
Aluminum Hydraulic Shoring means a manufactured shoring system consisting
of aluminum hydraulic cylinders (crossbraces) used with vertical rails (uprights)
or horizontal rails (wales). Such system is designed to support the sidewalls
of an excavation and prevent cave-ins. See Figure 2.0.
Bell-bottom pier hole means a type of shaft or footing excavation,
the bottom of which is made larger than the cross section above to form
a belled shape.
 |
Figure 1.0 -
Benching System |
Benching (Benching system) is a method of protecting employees from
cave-ins by excavating the sides of an excavation to form one or more horizontal
steps, usually with vertical or near-vertical surfaces between levels.
Cave-in means the movement of soil or rock into an excavation, or
the loss of soil from under a trench shield or support system, in amounts
large enough to trap, bury, or injure and immobilize a person.
Competent person means one who has been trained to identify hazards
in the workplace, or working conditions that are unsafe for employees, and
who has the authority to have these hazards corrected. The departmental
Project Manager serves as the departmental competent person for the purposes
of this program. The Project Manager will conduct all required tests and
inspections as detailed in this program, and ensure that employees working
in excavations have been trained and are following the requirements of this
program.
Cross braces mean the horizontal members of a shoring system installed
from side to side of the excavation. The cross braces bear against either
uprights or Wales See Figure 2.0.
Department means a department at the university that conducts work
in excavations.
Excavation means any man-made cut, cavity, trench, or depression
in an earth surface formed by earth removal.
Faces or sides mean the vertical or inclined earth surfaces formed
as a result of excavation work.
Failure means the movement or damage of a structural member or connection
that makes it unable to support loads.
Hazardous atmosphere means an atmosphere that is explosive, flammable,
poisonous, corrosive, oxidizing, irritating, oxygen deficient, toxic, or
otherwise harmful, that may cause death, illness, or injury.
Kickout means the accidental movement or failure of a cross brace.
Project Manager is the individual within the department that will
oversee excavation work and that is responsible for assuring compliance
with this program.
Protective system means a method of protecting employees from cave-ins,
from material that could fall or roll from an excavation face into an excavation,
or from the collapse of adjacent structures. Protective systems include
support systems, sloping and benching systems, shield systems, and other
systems that provide the necessary protection.
Ramp means an inclined walking or working surface that is used to
gain access to one point from another. A ramp may be constructed from earth
or from structural materials such as steel or wood.
Registered Professional Engineer means a person who is registered
as a professional engineer in Virginia.
Safety Coordinator means the individual at Environmental Health and
Safety Services (EHSS) responsible for developing and implementing this
program, conducting unannounced work site inspections, and ensuring that
the departments comply with the program requirements.
Sheeting means the members of a shoring system that retain the earth
in position and in turn are supported by other members of the shoring system.
See figure 2.0.
Shield (Shield system) means a structure used in an excavation to
withstand cave-ins and which will protect employees working within the shield
system. Shields can be permanent structures or portable units moved along
as work progresses. Shields used in trenches are usually referred to as
"trench boxes" or "trench shields."
Shoring (Shoring system) means a structure that is built or put in
place to support the sides of an excavation to prevent cave-ins.
Sides. See "Faces."
Sloping (Sloping system) means sloping the sides of the excavation
away from the excavation to protect employees from cave-ins. The required
slope will vary with soil type, weather, and surface or near surface loads
that may affect the soil in the area of the trench (such as adjacent buildings,
vehicles near the edge of the trench and so forth).
Stable rock means natural solid mineral material that can be excavated
with vertical sides that will remain intact while exposed.
Structural ramp means a ramp built of steel or wood, usually used
for vehicle access. Ramps made of soil or rock are not considered structural
ramps.
Support system means a structure such as underpinning, bracing, or
shoring, which provides support to an adjacent structure, underground installation,
or the sides of an excavation.
Tabulated data means tables and charts approved by a registered professional
engineer and used to design and construct a protective system.
Trench (Trench excavation) means a narrow excavation (in relation
to its length) made below the surface of the ground.
Trench box or shield. See "Shield".
Uprights mean the vertical members of a trench shoring system placed
in contact with the earth and usually positioned so that individual members
do not contact each other. Uprights placed so that individual members are
closely spaced, in contact with or interconnected to each other, are often
called "sheeting."
Wales are horizontal members of a shoring system placed in the direction
of the excavation face whose sides bear against the vertical members of
the shoring system or earth (the uprights or sheeting).
3.0 PROGRAM ELEMENTS
3.1 Training and Duties of Program Participants
- All personnel
involved in trenching or excavation work shall be trained in the requirements
of this program. Departmental personnel shall be trained by the departmental
Project Manager with assistance from the Safety Coordinator at EHSS.
- Training shall
be performed before the employee is assigned duties in excavations.
- Retraining will
be performed whenever work site inspections conducted by the Project
Manager or EHSS indicate that an employee does not have the necessary
knowledge or skills to safely work in or around excavations.
- Training records
will be maintained by the Project Manager and will be copied to the
Safety Coordinator at EHSS. These records shall include the date(s)
of the training program, the instructor(s) of the training program,
a copy of the written material presented, and the names of the employee(s)
to whom the training was given.
3.2
Training and Duties of Workers
All personnel that perform work in excavations shall comply with the requirements
of this program. These personnel shall receive appropriate training that
shall include, at a minimum:
- The work practices
that must be followed during excavating or working in excavations;
- The use of
personal protective equipment that will typically be required during
work in excavations, including but not limited to safety shoes,
hard-hats, and fall protective devices;
- Procedures
to be followed if a hazardous atmosphere exists or could reasonably
be expected to develop during work in an excavation; and,
- Emergency
and non-entry rescue methods, and procedure for calling rescue services.
3.3
Training and Duties of the Project Manager
The Project Manager shall receive the training detailed above and shall,
in addition, receive training on the requirements detailed in Section 4.0
and 5.0, and Appendices A through D of this program. The Project Manager
shall:
A.Coordinate and
actively participate in the training of departmental employees. A copy
of the training records shall be maintained by the Project Manager, and
shall be copied to EHSS;
B.Ensure on a daily basis, or more often as detailed in this program,
that work site conditions are safe for employees to work in excavations;
C.Determine the means of protection (sloping back the sides of the excavation,
use of trench shields, or shoring) that will be used for each excavation
project; and,
D.Ensure, if required, that the design of a protective system has been
completed and approved by a Registered Professional Engineer before work
is begun in the excavation.
3.4
Contractor Awareness, Duties and Responsibilities
A.A Contractor
that is performing excavation work on university property shall coordinate
trenching and excavation work with the Project Manager to assure
the coordination of the work and shutdown of utilities if necessary.
B.Additional information is included in Virginia Tech’s Safety Guide
for Contractors and Subcontractors
4.0
SPECIFIC EXCAVATION REQUIREMENTS
4.1 Utilities and Pre-work Site Inspection. Prior
to excavation the site shall be thoroughly inspected by the Project Manager
to determine if special safety measures must be taken.
Surface encumbrances. All equipment, materials, supplies, permanent
installations (for example, buildings or roadways), trees, brush, boulders
and other objects at the surface that could present a hazard to employees
working in the excavation shall be removed or supported as necessary to
protect employees.
Underground installations.
The location of sewers,
telephone, fuel, electric, water lines, or any other underground installations
that may be encountered during excavation work shall be determined and
marked prior to opening an excavation. Arrangements shall be made as necessary
by the Project Manager with the appropriate utility agency for the protection,
removal, shutdown, or relocation
of underground installations.
If it is not possible to establish the exact location of these installations,
the work may proceed with caution if detection equipment or other safe
and acceptable means are used to locate the utility.
Excavation shall be done in a manner that does not endanger the underground
installations or the employees engaged in the work. Utilities left in
place shall be protected by barricades, shoring, suspension or other means
as necessary to protect employees.
4.2
Protection of the Public: Barricades, walkways, lighting and posting
shall be provided as necessary for the protection of the public prior to
the start of excavation operations.
Guardrails, fences, or barricades shall be provided on excavations adjacent
to walkways, driveways and other pedestrian or vehicle thoroughfares. Warning
lights or other illumination shall be maintained as necessary for the safety
of the public and employees from sunset to sunrise.
Wells, holes, pits, shafts and all similar hazardous excavations shall be
effectively barricaded or covered and posted as necessary to prevent unauthorized
access. All temporary excavations of this type shall be backfilled as soon
as possible.
Walkways or bridges protected by standard guardrails shall be provided where
employees and the general public are permitted to cross over excavations.
Where workers in the excavation may pass under these walkways or bridges,
a standard guardrail and toeboard shall be used. Information on the requirements
for guardrails and toeboards may be obtained by contacting EHSS.
4.3 Protection of Workers in Excavations
Access and means of egress. Stairs, ladders or ramps shall be provided
where employees are required to enter trench excavations over 4 feet deep.
The maximum distance of lateral travel (e.g., along the length of the trench)
required to reach the means of egress shall not exceed 25 feet.
Structural ramps.
Structural ramps
used solely by employees as a means of access or egress from excavations
shall be designed by a competent person. Structural ramps used for access
or egress of equipment shall be designed by a person qualified in structural
design, and shall be constructed in accordance with the design.
Ramps and runways constructed of two or more structural members shall
have the structural members connected together to prevent movement or
displacement.
Structural members used for ramps and runways shall be of uniform thickness.
Cleats or other appropriate means used to connect runway structural members
shall be attached to the bottom of the runway or shall be attached in
a manner to prevent tripping.
Structural ramps used in place of steps shall be provided with cleats
or other surface treatments on the top surface to prevent slipping.
Ladders.
When portable ladders
are used, the ladder side rails shall extend a minimum of 3 feet above
the upper surface of the excavation (see Figure 3.0).
Ladders shall have nonconductive side rails if work will be performed
near exposed energized equipment or systems.
Two or more ladders, or a double-cleated ladder, will be provided where
25 or more employees will be conducting work in an excavation where ladders
serve as the primary means of egress, or where ladders serve two-way traffic.
Ladders will be inspected prior to use for signs of damage or defects.
Damaged ladders will be removed from service and marked with "Do
Not Use" until repaired.
 |
Figure
3.0 - Ladder Safety |
Ladders shall be used only on stable and level surfaces unless secured.
Ladders placed in any location where they can be displaced by workplace
activities or traffic shall be secured, or barricades shall be used to
keep these activities away from the ladder.
Non-self-supporting ladders shall be positioned so that the foot of the
ladder is one-quarter of the working length away from the support (see
Figure 3.0).
Employees shall not be allowed to carry any object or load while on the
ladder that could cause them to lose their balance and fall.
Exposure to vehicular
traffic. Employees exposed to vehicular traffic shall be provided with,
and shall wear, warning vests or other suitable garments marked with or
made of reflectorized or high-visibility material. Warning vests worn by
flagmen shall be red or orange, and shall be of reflectorized material if
worn during night work.
Employee exposure to falling loads. No employee shall be permitted
underneath loads handled by lifting or digging equipment. Employees shall
be required to stand away from any vehicle being loaded or unloaded to avoid
being struck by any spillage or falling materials. Operators may remain
in the cabs of vehicles being loaded or unloaded when the vehicles provide
adequate protection for the operator during loading and unloading operations.
Warning system for mobile equipment. A warning system shall be used
when mobile equipment is operated adjacent to the edge of an excavation
if the operator does not have a clear and direct view of the edge of the
excavation.The warning system shall consist of barricades, hand or mechanical
signals, or stop logs. If possible, the grade should be away from the excavation.
Hazardous atmospheres. The Project Manager will test the atmosphere
in excavations over 4 feet deep if a hazardous atmosphere exists or could
reasonably be expected to exist. A hazardous atmosphere could be expected,
for example, in excavations in landfill areas, in excavations in areas where
hazardous substances are stored nearby, or in excavations near or containing
gas pipelines.
Adequate precautions
shall be taken to prevent employee exposure to atmospheres containing
less than 19.5 percent oxygen and other hazardous atmospheres. These precautions
include providing proper respiratory protection or forced ventilation
of the workspace. Technical assistance on these precautions may be obtained
by contacting EHSS.
Forced ventilation or other effective means shall be used to prevent employee
exposure to an atmosphere containing a flammable gas in excess of 10 percent
of the lower flammability limit of the gas.
2When controls are used that are intended to reduce the level of atmospheric
contaminants to acceptable levels, continuous air monitoring will be performed
by the Project Manager. The device used for atmospheric monitoring shall
be equipped with an audible and visual alarm.
3Atmospheric testing will be performed using a properly calibrated direct
reading gas monitor. Direct reading gas detector tubes or other acceptable
means may also be used to test potentially toxic atmospheres.
4Each atmospheric testing instrument shall be calibrated on a schedule
and in the manner recommended by the manufacturer except:
0Any atmospheric
testing instrument that has not been used within thirty (30) days shall
be recalibrated by the Department prior to use.
1Each atmospheric testing instrument shall be calibrated at least every
six (6) months by the Department.
2Copies of calibration records will be forwarded to EHSS.
Each atmospheric testing instrument will be field checked immediately
prior to use to ensure that it is operating properly.
Personal protective
equipment.
All employees working
in trenches or excavations shall wear approved hard-hats and steel toed
shoes or boots.
Employees exposed to flying fragments, dust, or other materials produced
by drilling, sawing, sanding, grinding and similar operations shall wear
approved safety glasses with side shields.
Employees exposed to hazards produced by, or performing, welding, cutting,
or brazing operations shall wear, as determined by the Project Manager,
approved spectacles or a welding faceshield or helmet.
Employees entering bell-bottom pier holes or other similar deep and confined
footing excavations shall wear a harness with a lifeline securely attached
to it. The lifeline shall be separate from any line used to handle materials
and shall be individually attended at all times while the employee wearing
the lifeline is in the excavation.
Employees shall wear, as determined by the Project Manager, approved gloves
or other suitable hand protection.
Employees using, or working in the immediate vicinity of, hammer drills,
masonry saws, jackhammers or similar high noise producing equipment shall
wear suitable hearing protection.
Each employee at the edge of an excavation 6 feet or more deep shall be
protected from falling. Fall protection shall be provided by guardrail
systems, fences, barricades, covers, or a tie-back system meeting the
requirements of the Virginia Tech Fall Protection Program.
Emergency rescue equipment, such as breathing apparatus, a safety harness
and line, and a basket stretcher shall be readily available where hazardous
atmospheric conditions exist or may develop during work in an excavation.
This equipment shall be attended when in use. Only personnel that have
received approved training and have appropriate equipment shall attempt
retrieval that would require entry into a hazardous atmosphere. If entry
into a known hazardous atmosphere must be performed, then EHSS shall be
given advance notice so that the hazards can be evaluated and rescue personnel
placed on standby if necessary.
Walkways and guardrails.
Walkways shall be provided where employees or equipment are permitted to
cross over excavations. Guardrails shall be provided where walkways, accessible
only to on-site project personnel, are 6 feet or more above lower levels.
Protection from hazards associated with water accumulation.
Employees shall not
work in excavations that contain or are accumulating water unless precautions
have been taken to protect employees against the hazards posed by water
accumulation. The precautions taken could include, for example, special
support or shield systems to protect from cave-ins, water removal to control
the level of accumulating water, or use of safety harnesses and lifelines.
If water is controlled or prevented from accumulating by the use of water
removal equipment, the water removal equipment andoperation shall be monitored
by a person trained in the use of the equipment.
If excavation work interrupts the natural drainage of surface water (such
as streams), diversion ditches, dikes, or other suitable means shall be
used to prevent surface water from entering the excavation. Precautions
shall also be taken to provide adequate drainage of the area adjacent
to the excavation. Excavations subject to runoff from heavy rains shall
be reinspected by the Project Manager to determine if precautions detailed
in section 4.3(G)(1) and/or 4.3(G)(2) should be taken.
The Project Manager shall inform workers of the precautions or procedures
that are to be followed if water accumulates or is accumulating in an
excavation.
Stability of adjacent
structures. The Project Manager will determine if the excavation work
could affect the stability of adjoining buildings, walls, sidewalks or other
structures.
Support systems (such
as shoring, bracing, or underpinning) shall be used to assure the stability
of structures and the protection of employees where excavation operations
could affect the stability of adjoining buildings, walls, or other structures.
Excavation below the level of the base or footing of any foundation or
retaining wall that could be reasonably expected to pose a hazard to employees
shall not be permitted except when: A support system, such as underpinning,
is provided to ensure the safety of employees and the stability of the
structure; or
The excavation is in stable rock; or
A registered professional engineer has approved the determination that
the structure is sufficiently removed from the excavation so as to be
unaffected by the excavation activity; or
A registered professional engineer has approved the determination that
such excavation work will not pose a hazard to employees.
Sidewalks, pavements and appurtenant structure shall not be undermined
unless a support system or other method of protection is provided to protect
employees from the possible
collapse of such structures.
Where review or approval of a support system by a registered professional
engineer is required, the Department shall secure this review and approval
in writing before the work is
begun. A copy of this approval shall be provided to EHSS.
Protection of employees
from falling objects and loose rocks or soil.
Adequate protection
shall be provided to protect employees from loose rock or soil that could
pose a hazard by falling or rolling from an excavation face. Such protection
shall consist of:
Scaling to remove
loose material;
Installation of protective barricades, such as wire mesh or timber,
at appropriate intervals on the face of the slope to stop and contain
falling material; or
Benching sufficient to contain falling material.
Excavation personnel shall not be permitted to work above one another
where the danger of falling rock or earth exists.
Employees shall be protected from excavated materials, equipment or other
materials that could pose a hazard by falling or rolling into excavations.
Protection shall
be provided by keeping such materials or equipment at least 2 feet
from the edge of excavations, by the use of restraining devices that
are sufficient to prevent materials or equipment from falling or rolling
into excavations, or by a combination of both if necessary.
Materials and equipment may, as determined by the Project Manager, need
to be stored further than 2 feet from the edge of the excavation if
a hazardous loading condition is created on the face of the excavation.
Materials piled, grouped or stacked near the edge of an excavation must
be stable and self-supporting.
4.4
Inspection by the Project Manager
The departmental
Project Manager shall conduct daily inspections of excavations, adjacent
areas, and protective systems for evidence of a situation that could result
in possible cave-ins, failure of protective systems, hazardous atmospheres,
or other hazardous conditions. An inspection shall be conducted by the
Project Manager prior to the start of work and as needed
throughout the shift. Inspections shall also be made after every rainstorm
or other hazard increasing
occurrence. These inspections are only required when the trench
will be or is occupied by employees.
Where the competent person finds evidence of a situation that could result
in a possible cave-in, failure of protective systems, hazardous atmosphere,
or other hazardous conditions, exposed employees shall be removed from
the hazardous area until precautions have
been taken to assure their safety.
The Project Manager shall maintain a written log of all inspections conducted.
This log shall include the date, work site location, results of the inspection,
and a summary of any action taken to correct existing hazards.
5.0
REQUIREMENTS FOR PROTECTIVE SYSTEMS.
5.1 Protection of employees in excavations.
Employees in an excavation
shall be protected from cave-ins by using either an adequate sloping and
benching system (Section 5.2) or an adequate support or protective system
(Section 5.3). The only exceptions are:
Excavations made
entirely in stable rock; or
Excavations less than 5 feet in depth where examination of the
ground by the Project Manager provides no indication of a potential
cave-in.
Protective systems shall be capable of resisting all loads that could
reasonably be expected to be applied to the system.
5.2
Design of sloping and benching systems. The slope and configuration
of sloping and benching systems shall be selected and constructed by the
Project Manager in accordance with either Section 5.2 (A), (B), (C)
or (D) as follows:
5.3
Design of support systems, shield systems, and other protective systems.
The design of support systems , shield systems, and other protective systems
shall be selected and constructed by the Project Manager in accordance with
the requirements of either Section 5.3 (A), (B), (C) or (D) as follows:
Option (1) - Designs
using Appendix A, C and D. Design of timber shoring in trenches shall
be made in accordance with the requirements of appendix A and C of this
program. Design of aluminum hydraulic shoring shall be in accordance with
Section 5.2(B), but if manufacturer’s tabulated data can not be used,
then designs shall be in accordance with appendix D.
Option (2) - Designs using manufacturer’s tabulated data.
Support systems,
shield systems, or other protective systems drawn from manufacturer’s
tabulated data shall be constructed and used in accordance with all
specifications, recommendations, and limitations issued or made by the
manufacturer.
Deviation from the specifications, recommendations, and limitations
issued or made by the manufacturer shall only be allowed after the manufacturer
issues specific written approval.
Manufacturer’s specifications, recommendations, and limitations,
and manufacturer’s approval to deviate from the specifications,
recommendations, and limitations shall be kept in written form at the
jobsite during construction of the protective system. After that time
this data may be stored off the jobsite, but a copy shall be made available
to EHSS upon request.
Option (3) - Designs using other tabulated data.
Designs of support systems, shield systems, or other protective systems
shall be selected from and be constructed in accordance with tabulated
data, such as tables and charts.
The tabulated data shall be in written form and include all of the following:
Identification
of the factors that affect the selection of a protective system drawn
from such data;
Identification of the limits of use of the data;
Information needed by the user to make a correct selection of a protective
system from the data.
At least one copy of the tabulated data, which identifies the registered
professional engineer who approved the data, shall be maintained at the
jobsite during construction of the protective system. After that time
the data may be stored off the jobsite, but a copy of the data shall be
made available to EHSS upon request.
Option (4) - Design by a registered professional engineer.
Support systems, shield systems, and other protective systems not using
the options detailed in sections 5.3(A), (B) or (C) shall be approved
by a registered professional engineer.
Designs shall be in written form and shall include the following:
A plan indicating
the sizes, types, and configurations of the materials to be used in
the protective system; and
The identify of the registered professional engineer approving the design.
At least one copy of the design shall be maintained at the jobsite during
construction of the protective system. After that time, the design may
be stored off the jobsite, but a copy of the design shall be made available
to EHSS upon request.
5.4
Materials and equipment.
Materials and equipment
used for protective systems shall be free from damage or defects that
might affect their proper function.
Manufactured materials and equipment used for protective systems shall
be used and maintained in accordance with the recommendations of the manufacturer,
and in a manner that will prevent employee exposure to hazards.
When material or equipment used for protective systems are damaged, the
Project Manager shall ensure that these systems are examined by a competent
person to evaluate its suitability for continued use. If the competent
person can not assure the material or equipment is able to support the
intended loads or is otherwise suitable for safe use, then such material
or equipment shall be removed from service. These materials or equipment
shall be evaluated and approved by a registered professional engineer
before being returned to service.
5.5
Installation and removal of support
General.
Members of support
systems shall be securely connected together to prevent sliding, falling,
kickouts, or other potential hazards.
Support systems shall be installed and removed in a manner that protects
employees from cave-ins, structural collapses, or from being struck by
members of the support system.
Individual members of support systems shall not be subjected to loads
exceeding those which those members were designed to support.
Before temporary removal of individual support members begins, additional
precautions shall be taken as directed by the Project Manager to ensure
the safety of employees. These precautions could include, for example,
the installation other structural members to carry the loads imposed on
the support system.
Removal of support systems shall begin at, and progress from, the bottom
of the excavation. Members shall be released slowly. If there is any indication
of possible failure of the remaining members of the structure or possible
cave-in of the sides of the excavation the work shall be halted until
it can be examined by the Project Manager.
Backfilling shall progress together with the removal of support systems
from excavations.
Additional requirements
for support systems for trench excavations.
Excavation of material
to a level no greater than 2 feet below the bottom of the members of a
support system is allowed, but only if the system is designed to resist
the forces calculated for the full depth of the trench. There shall be
no indications while the trench is open of a possible loss of soil from
behind or below the bottom of the support system.
Installation of a support system shall be closely coordinated with the
excavation of trenches.
5.6
Sloping and benching systems. Employees shall not be permitted to work
above other employees on the faces of sloped or benched systems except whe0n
employees at the lower levels are protected from the hazard of falling,
rolling, or sliding material or equipment.
5.7 Shield systems
General.
Shield systems shall
not be subjected to loads that are greater than those they were designed
to withstand.
Shields shall be installed in a manner that will restrict lateral or other
hazardous movement of the shield that could occur during cave-in or unexpected
soil movement.
Employees shall be protected from the hazard of cave-ins when entering
or exiting the areas protected by shields.
Employees shall not be allowed in shields when shields are being installed,
removed, or moved vertically.
Additional requirement
for shield systems used in trench excavations. Excavation of material
to a level no greater than 2 feet below the bottom of the shield system
is allowed, but only if the system is designed to resist the forces calculated
for the full depth of the trench. There shall be no indications while the
trench is open of a possible loss of soil from behind or below the bottom
of the shield system.
This paper appears in the eLCOSH website with the permission of the author
and/or copyright holder and may not be reproduced without their consent. eLCOSH is an
information clearinghouse. eLCOSH and its sponsors are not responsible for the accuracy of
information provided on this web site, nor for its use or misuse.
|